H Seismic Hurricane Ties
H10 Installation
H10-2 Installation
(H11Z similar)
19
20
H14 Installation
to double top plates
21
16
18
Hurricane Tie Installations to
Achieve Twice the Load (Top View)
Install diagonally across
from each other for
minimum 2x truss.
For H2.5A only -
Products can be on the
same side of the wall
provided they are
configured as shown.
Nailing into both sides of
a single ply 2x truss may
cause the wood to split.
H9 attaching
truss to top
plates
14
H7Z Installation
H8 attaching
stud to sill
(4-8d into plate,
5-8d into stud)
H8 attaching
I-joist to double
top plates
H9, H10 and H10R optional positive angle nailing connects shear blocking
to rafter. Use 8d common nails. Slot allows maximum field-bending up to
a pitch of 6/12, use 75% of the table uplift load; bend one time only.
17
Considerations for Hurricane Tie Selection
1. What is the uplift load?
2. What is the parallel-to-plate load?
3. What is the perpendicular-to-plate load?
4. What is the species of wood used for the rafter and the top plates?
(Select the load table based on the lowest performing species of wood.)
5. Will the hurricane tie be nailed into both top plates or the upper
top plate only?
6. What load or loads will the hurricane tie be taking?
7. Select hurricane tie based on performance, application, installed cost
and ease of installation.
Allowable simultaneous loads in more than one direction on a single
connector must be evaluated as follows:
Design Uplift/Allowable Uplift Design Lateral Parallel to Plate
Allowable Lateral Parallel to Plate Design Lateral Perpendicular to
Plate Allowable Lateral Perpendicular to Plate 1.0.
2
1
15
H8 attaching
rafter to double
top plates
H14 Installation
to double 2x header
22
VB Knee Braces
The VB provides lateral resistance force at the bottom of beams
when installed approximately 45 or more to the vertical plane.
MATERIAL: 12 gauge. FINISH: Galvanized
INSTALLATION: Use specified fasteners. See General Notes. 16-N54A fasteners are included with the brace.
CODES: See page 12 for Code Listing Key Chart.
Model
No.
H
(Beam Depth)
L
Fasteners
(Total)
Allowable Tension Loads 1
Floor (100)
Roof (125)
VB5
10" 15"
5'
16-N54A
990
1240
VB7
15" 22
"
7'
16-N54A
990
1240
VB8
22
" 28
"
8'
16-N54A
990
1240
VB10
28
" 36"
10'
16-N54A
990
1240
VB12
36" 42"
12'
16-N54A
990
1240
Code
Ref.
3, 39, 88,
121
Typical VB Installation
1.Roof loads have been increased 25% with no further increase allowed.