Page 38 of Wood Construction Connectors 2006 Catalog by Simpson Strong-Tie
39
Anchors
HDA/HD Holdowns
Model
No.
Material
Dimensions
Fasteners
Body
Ga
Base
Ga
HB 4
SB
W
H
B
SO
CL
Anchor
Dia 5
Stud
Machine Bolts
Qty
Dia
HD2A
7
12
4
2
2
8
2
1
2
HD5A
3
10
5
3
3
9
3
2
2
HD6A
7
6
3
3
11
3
2
2
HD8A
7
6
3
3
14
3
2
3
HD10A
7
6
3
3
18
3
2
4
HD14A
3
7
4
3
20
3
2
1
4
1
HD15
3
7
4
3
24
4
3
2
1
5
1
Model
No.
HD2A
HD5A
HD6A
HD8A
HD10A
HD14A
HD15
Code
Ref.
Wood Member Thickness
1
2
2
3
3
5
1320
1740
2165
2570
2565
2550
0.058
1585
2110
2625
3130
3645
3680
0.067
1870
2470
3065
3680
4280
5020
0.041
2710
3655
4530
5480
6350
7330
0.111
3275
4600
5745
7045
8160
9195
0.269
9495
12485
0.215
13810
0.082
0.077
0.117
0.125
0.121
0.269
0.282
0.082
40, 105,
122
Holdown 9
Deflection
at Highest
Allowable
Design
Load
Holdown 9
Deflection
at Highest
Allowable
Design Load
Raised
Wood Member Thickness
1
2
2
3
3
5
1555
2055
2565
2775
2775
2760
1870
2485
3095
3705
4010
3980
2275
2980
3685
4405
5105
5510
3220
4350
5415
6465
7460
7910
3945
5540
6935
8310
9540
9900
11080
13380
15305
Allowable Tension Loads
DF/SP (133/160)
Allowable Tension Loads
SPF/HF (133/160)
8. See page 13-15 for testing and other important information.
9. Deflection at Highest Allowable Design Load:
The deflection of a holdown measured between the anchor bolt and the strap portion
of the holdown when loaded to the highest allowable load listed in the catalog table.
This movement is strictly due to the holdown deformation under a static load test
conducted on a steel jig. All other sources of deflection shall be in addition.
10. When using structural composite lumber columns, bolts must be applied to the
wide face of the column.
11. The Designer shall reduce the allowable loads shown per NDS requirements
when bolt threads are in the shear plane.
12. HDA and HD allowable loads are based on the lower of the 2001 NDS fastener
values or the ultimate load on a steel test jig divided by 2.5.
13. Post design shall be by Designer.
1. Allowable loads have been increased for earthquake or wind load durations with
no further increase allowed; reduce where other load durations govern.
2. HD15 requires a minimum 4x8 (in a 3 wide shearwall) or a 6x6 nominal post
to ensure the tension load carrying capacity of the critical net section meets the
holdown capacity.
3. Use a minimum 4x6 nominal post for the HD14A. Minimum post size is
required to ensure the tension load carrying capacity of the critical net section
meets the holdown capacity.
4. HB is the required minimum distance from the end of the stud to the center of the
first stud bolt hole. End distance may be increased as necessary for installation.
5. The designer must specify anchor bolt type, length and embedment.
See SSTB Anchor Bolts (page 33-34) and Additional Anchor Designs (page 34).
6. See page 21 and 29 for anchor bolt retrofit.
7. Lag bolts will not develop the listed loads.
See notes below.
A B and F do not apply
to the PHD and HDQ.
A. Bolt slip can occur at holdown stud bolts.
B. Increased bolt slip can occur if oversized holes are drilled through the
stud for holdown stud bolts (oversized holes are when the hole diameter
is greater than the bolt diameter plus per 2001 NDS 11.1.2).
C. When a holdown is installed on only one side of the stud, an eccentricity
exists during loading which can cause more movement in the shearwall
system.
D. Unrestrained anchor bolt nuts can spin loose during cyclic loading; using
steel nylon locking nuts or thread adhesive may prevent nut spin.
E.
Movement can occur when nuts are not tightened enough. Retightening
bolts before covering wall may prevent this.
F.
Deflection can occur in the holdown under load caused by stresses due
to earthquake or high wind.
G. Lateral displacement at the top of the wall rotates the stud around its
base causing the holdown base plate to displace vertically.
H. Wood shrinkage can occur due to drying of the sill plate, rim joist, and/or
top plate; nuts may require retightening.
I.
Uplift forces on the bolts can cause localized wood crushing at bolt
bearing locations. Using larger bearing plates may prevent this.
J.
Wood at the end of the studs (sill plates, rim joists, etc.) may crush
under normal dead and live loading; additional compressive forces due
to overturning during earthquake and high wind loads add to the
deflection.
BPs are required
by the City of
Los Angeles.
Check with your
local building
code on usage.
(NDS Section 11.1.2.3
requires a metal
plate, metal strap,
or minimum of a
standard cut washer.)
Available with additional corrosion protection. Check with factory.
SOURCES OF DEFLECTION AT SHEARWALL HOLDOWN CONNECTIONS